This is as far as our pool got with Trey Jones/PDG. It sat in the same condition for three months before we fired Trey.

 

To put some perspective around the delays and my saying "many deadlines missed," We were originally told that it would take two months to complete the entire project.

 

Here is a brief timeline of the missed projected completion dates provided to us by Trey:

  • Mid-March 2018
  • May 1st

  • June 1st

  • July 1st

  • July 15th

  • August 1st

On August 6, 2018, with the project about half done, we fired Trey Jones/PDG, and another pool company came in and finished our pool in one week.